On a construction job, profit is won or lost long before the final pay application goes out. Contractors who know where every job stands each month bid more sharply, catch cost overruns early, and walk into surety meetings with numbers they trust. That visibility starts with construction job costing and flows into your Alabama contractor WIP schedule (work-in-progress schedule), the report your bonding agent, surety, and banker will look at first. Here is how these pieces fit together for Alabama contractors, from cost codes to ASC 606 revenue recognition to bonding-ready financial statements. For the bigger picture, see what a construction accountant in Birmingham at Peters Bandura, LLC does for Alabama contractors.
Construction job costing: the foundation of every WIP schedule
Job costing means tracking every cost to the contract that caused it. A workable system usually includes:
- A consistent cost-code structure for labor, materials, subcontractors, equipment, and other direct costs, ideally matching how you build your estimates. That way you can compare estimate to actual line by line.
- Labor burden applied to jobs, not just gross wages. Payroll taxes, workers’ compensation, and benefits are real job costs.
- A reasonable method for job overhead and equipment. Allocate supervision, small tools, and company-owned equipment to jobs on a basis you can document and apply the same way every month.
- Change orders tracked separately until they are approved, so both the estimated contract value and estimated costs stay current.
- Monthly cost-to-complete updates from project managers. The WIP schedule is only as good as your estimate of the remaining costs.
Get these right and the WIP schedule becomes a byproduct of your bookkeeping, whether you work in QuickBooks or another system.
Building an Alabama contractor WIP schedule and reading over/under billings
A WIP schedule lists every open contract with its revised contract price, estimated total costs, costs to date, percent complete, revenue earned to date, billings to date, and the resulting over- or under-billing. Most contractors on the cost-to-cost method calculate percent complete as costs incurred to date divided by total estimated costs.
Illustration (hypothetical numbers): A $1,000,000 contract has estimated total costs of $800,000. You have spent $400,000, so the job is 50% complete and you have earned $500,000 of revenue. If you have billed $550,000, you are overbilled by $50,000. If you have billed $450,000, you are underbilled by $50,000.
- Overbillings (billings in excess of costs and estimated earnings) are a liability. Under ASC 606 this is a contract liability, because you have billed for work you have not yet performed. Moderate overbillings are common and can help cash flow, but they are cash you have not yet earned.
- Underbillings (costs and estimated earnings in excess of billings) are an asset, presented as a contract asset under ASC 606. Persistent or growing underbillings get a surety’s attention. They can mean slow billing, unapproved change orders, or a job whose costs are running ahead of its estimate.
Watch for profit fade, which is gross margin on a job shrinking from one month’s WIP to the next. It is often the earliest warning sign that a job is in trouble. When estimates show a contract will lose money, GAAP (ASC 605-35) requires you to recognize the entire anticipated loss as soon as it becomes evident, rather than spreading it over the remaining work.
Revenue recognition: ASC 606 for your books, Section 460 for your tax return
ASC 606 (GAAP financial statements)
ASC 606 replaced the old construction-specific guidance, though “percentage of completion” is still the everyday term. Under ASC 606-10-25-27, you recognize revenue over time if any one of three criteria is met:
- The customer receives and consumes the benefits as you perform;
- Your work creates or enhances an asset the customer controls as it is built (common when you build on the owner’s land); or
- Your work does not create an asset with an alternative use to you, and you have an enforceable right to payment for performance completed to date.
Most construction contracts meet at least one of these, so revenue is measured by progress, often with a cost-based input method. Under ASC 606, you also need to identify performance obligations, treat change orders and claims as contract modifications or variable consideration, and adjust for costs that do not reflect progress, such as materials delivered but not yet installed.
Section 460 (federal income tax)
Tax rules are separate from GAAP. Under Internal Revenue Code §460, income from a long-term contract generally must be reported using the percentage-of-completion method. When the contract is finished, a look-back interest calculation on Form 8697 settles the difference between your estimates and actual results.
Smaller contractors often qualify for an exception that allows other methods, such as completed-contract. It applies to a construction contract you estimate will be finished within two years of starting, if you meet the §448(c) gross receipts test for the year the contract is entered into. For tax years beginning in 2026, that test is met if your average annual gross receipts for the prior three tax years do not exceed $32,000,000, according to Revenue Procedure 2025-32. The 2025 tax law (P.L. 119-21) also broadened the exception from “home construction contracts” to “residential construction contracts.” See our 2026 residential construction contract change. This applies to contracts entered into in tax years beginning after July 4, 2025. Choosing or changing a method has long-term consequences, so plan it with your CPA as part of business tax preparation.
Bonding-ready financial statements
Sureties underwrite your balance sheet, your working capital, and your WIP. They generally want CPA-prepared financial statements, such as reviewed and compiled financial statements, with a contract schedule. How much CPA involvement they require (a compilation, a review, or an audit) is set by the surety, usually based on the size of your bonding program. Statements that make a strong impression usually have:
- A WIP schedule that ties to the balance sheet’s contract assets and liabilities and to revenue and cost on the income statement;
- A completed-contracts schedule showing how actual margins compared with estimates;
- Clean, aged receivables and payables, including retainage;
- Equipment and debt schedules that match the books; and
- Consistent, documented year-end cut-off.
Frequently asked questions
What is the difference between overbilling and underbilling?
Overbilling means you have billed more than you have earned based on percent complete. It is a liability (contract liability). Underbilling means you have earned more than you have billed. It is an asset (contract asset).
Will my surety accept reviewed or compiled financial statements?
It depends on your surety and the size of your bonding program. Peters Bandura, LLC prepares WIP schedules and reviewed and compiled financial statements, and gets your records ready for the audit firm you hire if your surety or lender requires audited statements.
Can a smaller contractor avoid percentage-of-completion for taxes?
Often, yes. Contracts expected to be finished within two years may qualify for an exception if your average annual gross receipts meet the §448(c) test, which is $32,000,000 for tax years beginning in 2026. Residential construction contracts have their own exception. Eligibility is determined contract by contract and year by year.
How often should we update our WIP schedule?
Monthly is best. At a minimum, update it at each quarter-end and whenever your surety or bank asks for interim statements. The cost-to-complete estimates from your project managers are what make it reliable.
Is ASC 606 the same as tax percentage-of-completion?
No. ASC 606 governs your GAAP financial statements. Section 460 governs your federal tax return. The two can produce different results, which is why many contractors track book and tax income separately.
Related: dyed diesel relief for Alabama farms, timber, and contractors.
How we can help
Peters Bandura, LLC helps contractors in Birmingham, Daphne and Baldwin County, and across Alabama set up job cost structures, prepare monthly WIP schedules, and produce reviewed and compiled financial statements that sureties and lenders can rely on. We also handle the tax side, including long-term contract method planning. Peters Bandura, LLC prepares reviews and compilations and gets your records ready for the audit firm you hire if your bonding program calls for one. Call our Birmingham office at (205) 547-0762 or our Daphne office at (251) 217-9280, or contact us to talk with our team.